Thermit Welding


Aluminothermic Welding of Railway Tracks

The article describes the process of Thermit welding (also known as thermite welding) using 39 photos taken by Christina Nöbauer on 14 October 2016 during construction work on the Pinzgauer Lokalbahn in Zell am See. This is a narrow-gauge railway with a gauge of 760 mm (Bosnian gauge) in the Austrian province of Salzburg.

  

The entire sequence lasted about half an hour, which is documented in the time stamps shown in the captions. The high-resolution photos can be enlarged by clicking on them. 

  

Process Sequence for Thermit Welding

The rails are already laid. The rail ends are cut with a flame cutter so that a 20 mm wide gap remains between the rail ends.

   

10:11:12 Preparation with less than 20 mm gap

© Wald1siedel, CC-BY-SA 4.0

10:19:45 Flame cuttiing to achieve 20 mm gap

© Wald1siedel, CC-BY-SA 4.0

10:20:48  Flame cuttiing to achieve 20 mm gap

© Wald1siedel, CC-BY-SA 4.0

   


After cutting to size, the rails are aligned against each other with a 1 m long ruler. Special attention must be paid to the clean vertical alignment of the rail top edge, because this has a high influence on the running surface and thus on the vibrations and running noise of the rail vehicles. The rail feet must also be mutually aligned so that there is as large as possible a contact surface for the weld metal at the rail ends.[1]

   

10:21:32 Cutting of the rear rail

© Wald1siedel, CC-BY-SA 4.0

   

10:26:44 Height adjustment with a wedge

© Wald1siedel, CC-BY-SA 4.0

   

10:27:09 Alignment of the rail using a 1 m long ruler

© Wald1siedel, CC-BY-SA 4.0

   


Split moulds are attached to the sides of the aligned rails and pressed onto the rail with retaining plates. The clamping device is attached to one of the two rail heads with the required dimensional adjustment and is later used to position the half moulds between the retaining plates.[2]

   

10:27:23 Preheating

© Wald1siedel, CC-BY-SA 4.0

   

10:27:49 Fixture

© Wald1siedel, CC-BY-SA 4.0

   

10:28:02 Fixture

© Wald1siedel, CC-BY-SA 4.0

   


The fixture is used for positioning and clamping the casting half moulds during pre-heating, casting and cool-down. The gaps between rails and casting half moulds are sealed with moulding sand compound.

   

10:28:51 Installation of the split moulds

© Wald1siedel, CC-BY-SA 4.0

 

10:29:31 Sealing with a quartz sand putty Wald1siedel, CC-BY-SA 4.0

   

10:32:06 Sealing with a quartz sand putty

© Wald1siedel, CC-BY-SA 4.0

   


The rail ends are dried and preheated. The flame of the gas burner is positioned above the casting half moulds. On multi-track lines, it is advisable to lay the gas supply hoses underneath the rails of the neighbouring track, so that the preheating process does not have to be interrupted when trains pass-by on the neighbouring track. Preheating ensures, among other things, that the rails do not cool down too quickly after welding, since if they cool down too quickly they become brittle and tend to brittle fracture.
   

10:33:01 Preheating

© Wald1siedel, CC-BY-SA 4.0

   

10:33:28 Preheating

© Wald1siedel, CC-BY-SA 4.0

   

10:34:17 Preheating

© Wald1siedel, CC-BY-SA 4.0

   


Today, the crucible or melting pot is often a ready-filled disposable metal bucket with a fireclay lining. It is positioned exactly above the sprue.[2] The vertical distance between the crucible and the split moulds should exeed 40 mm. The opening of the crucible must not touch the split moulds, because otherwise the plug will not be exposed, which would prevent the molten thermite steel from leaking out.[1]
 
Placing a crucible cap with a central hole insulates and protects against splashes, while the powder mixture is smoking due to the exothermic reaction. To be on the safe side, the igniter is added and ignited only after the assembly.[2]
 
In the past, casting was triggered manually, today it is usually done automatically by a melting plug. As soon as the metal is hot enough as a result of the exothermic reaction, the metal plug at the bottom of the crucible melts, which up to this point closes a hole in the bottom of the crucible. The molten metal then flows between the rail ends sealed with the split moulds and the quartzs sand putty
.[2]

  

10:37:58 Positio­ning of the crucible

© Wald1siedel, CC-BY-SA    

10:38:15 Begin of the exothermic reaction

© Wald1siedel, CC-BY-SA       

10:38:30 Molten metal runs from the crucible into the split moulds 

© Wald1siedel, CC-BY-SA 4.0

   


The molten steel runs into the mould and melts the rail ends. The molten weld metal fills the gap and overflows into two collecting pots at the riser channels, which have to be removed at a later stage.[2]

  

10:38:55 Casting process

© Wald1siedel, CC-BY-SA 4.0

   

10:39:04 After removing the crucible

© Wald1siedel, CC-BY-SA 4.0

      

10:39:43 Surplus material expelled throgh the risers 

© Wald1siedel, CC-BY-SA 4.0

   


The molten steel runs into the mould, fills it up and overflows along riser channels, melting the rail ends slightly.[2] After about 3 minutes the steel has solidified in the mould. Afterwards, the retaining plates which compressed the split moulds can be carefully removed.[1]
  

10:39:49 Solidification and cooling

© Wald1siedel, CC-BY-SA 4.0

   

10:40:22  Cooling

© Wald1siedel, CC-BY-SA 4.0

      

10:41:19  Removing the quartz sand putty

© Wald1siedel, CC-BY-SA 4.0

   


After solidification, the casting half moulds are only removed above the upper edge of the rail.

10:41:28 Removing the quartz sand putty

© Wald1siedel, CC-BY-SA 4.0

   

10:41:43 Removing the quartz sand putty

© Wald1siedel, CC-BY-SA 4.0

      

10:43:14 Removing the split moulds

© Wald1siedel, CC-BY-SA 4.0

   


The head bead above the top of the rail is carefully cut off with a hydraulic shearing device. The foot risers and the remaining parts of the moulds remain at the weld or at the rail, until the weld has cooled down. When cleaning the weld joint of moulding sand residues and remnants of the split moulds, the hot rail must not be touched by using the hammer ot other impact tools.[1]
  

10:43:18 Removing the split moulds

© Wald1siedel, CC-BY-SA 4.0

   

10:43:29  Preliminay removal of the spout

© Wald1siedel, CC-BY-SA 4.0

      

10:44:28 Shearing-off the spout

© Wald1siedel, CC-BY-SA 4.0

   


After shearing off the flash at the rail head, the running surface and the running edge are pre-ground while still hot.[1]
  

10:44:41 Shearing-off the risers

© Wald1siedel, CC-BY-SA 4.0

   

10:45:02   Cooling

© Wald1siedel, CC-BY-SA 4.0

      

10:45:17 Pre-grinding

© Wald1siedel, CC-BY-SA 4.0

   


Grinding is intended to achieve a rail surface and running edge that is as flat as possible, as it will come into contact with the running surfaces, wheel flange flanks and wheel flanges during operation.

   

10:46:11 Grinding

© Wald1siedel, CC-BY-SA 4.0

   

10:46:21 Grinding

© Wald1siedel, CC-BY-SA 4.0

      

10:46:34 Grinding

© Wald1siedel, CC-BY-SA 4.0

   


Finally, it must be assessed, whether the weld meets the quality requirements, before it is approved for railway operation.

  

10:47:43 Grinding

© Wald1siedel, CC-BY-SA 4.0

   

10:48:25 Finished weld after grinding

© Wald1siedel, CC-BY-SA 4.0

      

Another joint after making the second weld 

© Wald1siedel, CC-BY-SA 4.0

   


Did you know...

  • … that George Pellissier was the first American to use Thermit Welding commercially for laying 1 mile of track of the Holyoke Street Railway in Massachusetts?

See also

References

  1. Matthias Müller, Thorsten Schaeffer: Schweißverfahren mit Kurzvorwärmung (SkV). Gleisbau Welt (Memento of 18. März 2004 in Internet Archive) 2003–2012, retrieved on  20. April 2019.
        
  2. Helium 4 et al: Thermitreation. German Wikipedia, Creative-Commons-Lizence Attribution-ShareAlike 3.0 Unported (CC-BY-SA-3.0).

Licence

The text of this article is available under the „Creative Commons Attribution-ShareAlike 3.0 Unported“ (CC BY-SA 3.0) licence.